Officials share project plan, timeline for year two of Euclid Avenue reconstruction project in Pierre; Weekly public update meetings to be held starting March 11
Feb 20, 2026
A crowd of people gathered Thursday night (Feb. 19, 2026) to hear about timelines, see maps and have questions answered regarding the work that will be done this year to complete the Euclid Avenue reconstruction project in Pierre.
South Dakota Department of Transportation Pierre Region Engineer Dean
VanDeWiele (van-da-willy) said it’s DOT’s project, but they’re working closely with the City of Pierre and Morris, Inc. to ensure things go as smoothly as possible.
https://media-cdn.socastsrm.com/wordpress/wp-content/blogs.dir/2626/files/2026/02/022026-euclid1.mp3
VanDeWiele said construction work will occur in multiple places at the same time.
https://media-cdn.socastsrm.com/wordpress/wp-content/blogs.dir/2626/files/2026/02/022026-euclid2.mp3
Last year’s work primarily impacted business areas, but this year’s work on Euclid Avenue will create some temporary construction issues for both businesses and residential areas.
Morris, Inc. Division Manager TJ Gallagher said some preliminary work is already underway, but they’ll begin working in earnest in early March. He said there’s a lot of work to do so contractors will be putting in long days and long weeks.
https://media-cdn.socastsrm.com/wordpress/wp-content/blogs.dir/2626/files/2026/02/022026-euclid3.mp3
Safety is extremely important to Morris and Gallagher said in that aspect, they hope this year goes as well as the first year did.
https://media-cdn.socastsrm.com/wordpress/wp-content/blogs.dir/2626/files/2026/02/022026-euclid4.mp3
As part of the Euclid Avenue reconstruction project in Pierre, weekly update meetings will be held on Wednesday mornings. The updates will be at 11am in the Associated General Contractors building (300 E. Capitol Avenue, Suite 1) in Pierre. Enter through the door on Highland Avenue.
The overall completion date for the Euclid Avenue reconstruction project in Pierre is November 2026.
Euclid Project Web Page:
Throughout the reconstruction project, find additional information, including timelines, photos, and project maps at https://dot.sd.gov/euclid.